Create calendars for different working time measures in Base registers/PRO/Calendar.

  1. Click New and write in the year, same calendar number as before and name (if not, you must do the change in the employees' records in Base registers/Pro/Employees). Example: If your full time calendar number this year is 1, it has to be number 1 also the next year.
  2. Write in amount of expected working hours per day in the field Time/day.
  3. In the tab Working Days, you can click Import standard to import a standard calendar. Fill in which days that are working days and which are not. A working day is expressed as a digit with two decimals. A complete working day is 1,00, half day is 0,50 and a free day is 0,00. This enables different calendars for different working time measures.

You can copy working days from a calendar to another, as long as it is in the same year. Remember to change hours per day and the name after copying. Save the calendar.